Technical brief
BOQ - Stationary Type Fish Drier
Description
Unit Qty
Rate
01 Clearing and preparation of the site
Allow
Sum
02 Excavation of earth in wall and cubes and column Cubes
foundation
3.00
550.00
03 Approved earth filling under floors
600.00
04 Cement concrete 1:2:4 (3/4) in column bases,
positioning Kempas timber posts (4x4)
Cubes
1.00
20,000.00
05 Rubble work in foundation on cement motor1:5 up Cubes
to DPC level
1.4
12,000.00
06 ¾” thick dam proof course in cement and sand 1:2 Sqrs
1.2
4,500.00
07 Concrete screed to entire floor including ramp in Cubes
1:3:5 (3/4”) 3” thick
1.5
19,000.00
08 4 ½” thick brick work in walls up to a height of
Sqrs
2.00
5,450.00
09 Supply and installation of timber frames
10 Covering of roof and sides above brick walls with M 2
clear polythene
8.0 x 20
8 x 20 m
11 Fixing of drying platform using rolls
03 3500.00
12 Supply and installation of solar heat Aluminum
sheeting and brass tracks
Lft
125
50.00
13 Supply and installation of timber frames with
wooden door
1Nos
14 Supply installation of roof ventilators and chimney 2Nos
and ducting
15 2.5 wide Aluminum sheeting
151 ft
40
16 8 mm threaded bar
8Nos 675
17 Steel washers for above (16)
260 Nos
2.00
Amount
1,000.00
1,650.00
1,800.00
20,000.00
16,800.00
5,400.00
28,500.00
10,900.00
84,427.00
24640.00
10,500.00
10,500.00
5,000.00
50,000.00
6,000.00
3,037.00
520
Practical ActionConstruction and maintenances of solar fish drier Technical brief